What is the purpose of the Sprint Retrospective?

  1. To demonstrate the product to stakeholders
  2. To plan the next Sprint and select backlog items
  3. To inspect the product increment created during the Sprint
  4. To inspect how well the team worked together and identify improvements ✓

Correct answer: To inspect how well the team worked together and identify improvements

Option D is correct because the Sprint Retrospective is a formal opportunity for the Scrum Team to inspect itself, focusing on how team members collaborate, what went well, what problems occurred, and how processes and practices can be improved in the next Sprint. Option A is wrong because demonstrating the product increment to stakeholders is the purpose of the Sprint Review, not the Retrospective. Option B is incorrect because planning the next Sprint and selecting backlog items is the purpose of Sprint Planning. Option C is wrong because inspecting the product increment itself is also part of the Sprint Review, whereas the Retrospective focuses on the team's processes and interactions.

Topic: · sprint retrospective, scrum ceremonies, continuous improvement, psm

Practice Professional Scrum Master I (PSM I) Questions Free