According to the Scrum Guide, what is the maximum timebox for Sprint Planning when a team is running a two-week Sprint?
- 2 hours
- 4 hours ✓
- 8 hours
- 1 hour
Correct answer: 4 hours
Option B is correct because the Scrum Guide specifies that Sprint Planning is timeboxed to a maximum of eight hours for a one-month Sprint, and for shorter Sprints the event is proportionally shorter, resulting in a maximum of four hours for a two-week Sprint. Option A is incorrect because two hours is insufficient for a two-week Sprint; that duration might apply to a one-week Sprint. Option C is incorrect because eight hours is the maximum timebox for a full one-month Sprint, not a two-week Sprint. Option D is incorrect because one hour is far too short for Sprint Planning in a two-week Sprint and is not aligned with any Scrum Guide guidance.
Topic: · scrum guide, sprint planning, timebox, scrum events