Sprint Cancellation — Professional Scrum Master I (PSM I) Practice Questions

Sprint cancellation occurs when the Sprint Goal becomes obsolete, and only the Product Owner has the authority to cancel a Sprint. The PSM I exam tests this scenario specifically because it is one of the few cases where the Product Owner exercises direct control over the Sprint's continuation. Candidates must know that incomplete Product Backlog items are re-estimated and returned to the backlog, while completed and usable increments may be accepted. This concept is tested to ensure candidates understand the boundaries of each accountability in Scrum.

Free questions on sprint cancellation

Who can cancel a Sprint?
Free question · easy · full answer + explanation

More sprint cancellation questions in the full bank