What is the critical path in a project schedule?

  1. The path with the most tasks
  2. The path with the highest cost activities
  3. The longest path through the project network determining minimum duration ✓
  4. The path that requires the most resources

Correct answer: The longest path through the project network determining minimum duration

Option C is correct because the critical path is defined in network scheduling (CPM/PERT) as the longest sequence of dependent activities from project start to finish, and it determines the minimum total project duration; any delay on the critical path directly extends the project end date. Option A is wrong because the number of tasks on a path is irrelevant; a path with fewer but longer-duration tasks can still be the critical path. Option B is wrong because cost is not a factor in identifying the critical path, which is based solely on activity durations and dependencies. Option D is wrong because resource intensity does not define the critical path; resource leveling is a separate scheduling concern that may shift activities but does not determine which path governs project duration.

Topic: · critical path method, project scheduling, cpm, project management

Practice PMP - Project Management Professional Questions Free