Cpi — PMP - Project Management Professional Practice Questions

The Cost Performance Index (CPI) is an EVM metric calculated by dividing earned value by actual cost, expressing how efficiently the project is using its budget. A CPI greater than 1.0 indicates the project is delivering more value than the money spent, while a CPI below 1.0 signals a cost overrun. The PMP exam tests candidates on interpreting CPI values, using CPI to forecast the estimate at completion, and understanding the relationship between CPI and the Schedule Performance Index (SPI) when analyzing overall project health.

Free questions on cpi

A project manager discovers that the project is 10% over budget at the halfway point. Which metric shows this?
Free question · medium · full answer + explanation

More cpi questions in the full bank

Practice PMP - Project Management Professional Questions Free